Hi,
I need one information. Can we do looping among some stages of the job. For example say I have 7 stages then can I loop between stages 3,4,5 till certain condition in stage 3 satisfied.
Thanks,
looping among stages
Moderators: chulett, rschirm, roy
-
- Participant
- Posts: 54607
- Joined: Wed Oct 23, 2002 10:52 pm
- Location: Sydney, Australia
- Contact:
Basically no. There is already a loop of sorts within a job ("process each row").
In Job Sequences we have "activities" rather than stages, and two of these (version 7.5.1 and later) are called the StartLoop and EndLoop activities. With these you can loop around activities 3, 4 and 5.
In Job Sequences we have "activities" rather than stages, and two of these (version 7.5.1 and later) are called the StartLoop and EndLoop activities. With these you can loop around activities 3, 4 and 5.
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.