Hi,
I dont know what change we made(by mistake ), the color is not changing for the link while run. Iam just lookin out in Tools-->Option--->Graphical performance monitor, the refresh rate is 5Sec. And in administrator properties i dont find any relevent information. Do we have the option to check this anywhere.
I dont know what change we made(by mistake ), the color is not changing for the link while run. Iam just lookin out in Tools-->Option--->Graphical performance monitor, the refresh rate is 5Sec. And in administrator properties i dont find any relevent information. Do we have the option to check this anywhere.
-
- Participant
- Posts: 3593
- Joined: Thu Jan 23, 2003 5:25 pm
- Location: Australia, Melbourne
- Contact:
It's on the Diagram menu - Show performance statistics.
Certus Solutions
Blog: Tooling Around in the InfoSphere
Twitter: @vmcburney
LinkedIn:Vincent McBurney LinkedIn
Blog: Tooling Around in the InfoSphere
Twitter: @vmcburney
LinkedIn:Vincent McBurney LinkedIn
Re: No color change in link
Hi,
I faced this exact same problem...Your job would have executed correctly. The target tables would be populated but still you cannot see the link change color nor get the performance stats.
For this, I learnt from the forum that JobMonApp should be running. Make sure your JobMonApp is running. else you can start it by ./jobmoninit..
See the post in this forum for exact syntax etc.
Hope this helps.
Lalitha
I faced this exact same problem...Your job would have executed correctly. The target tables would be populated but still you cannot see the link change color nor get the performance stats.
For this, I learnt from the forum that JobMonApp should be running. Make sure your JobMonApp is running. else you can start it by ./jobmoninit..
See the post in this forum for exact syntax etc.
Hope this helps.
Lalitha
If you did ever stop the server for something and then restarted the server using these commands
$DSHOME/bin/uv -admin -stop
and
$DSHOME/bin/uv -admin -start
Then the JobMonApp also gets stopped by the "stop" command but does not get restarted with the "start " command...no explanation for that though.
$DSHOME/bin/uv -admin -stop
and
$DSHOME/bin/uv -admin -start
Then the JobMonApp also gets stopped by the "stop" command but does not get restarted with the "start " command...no explanation for that though.
Re: No color change in link
I have this same issue where in the performance statistics always returns 0rows/0secs and dont turn green on completion of job, though the job completes successfully returning rows...It happnes only in my project and in other's projects' it shows up...Is there a solution to get this performance statistics to appear truly [though it is SET ON]Lali_swam wrote:Hi,
I faced this exact same problem...Your job would have executed correctly. The target tables would be populated but still you cannot see the link change color nor get the performance stats.
For this, I learnt from the forum that JobMonApp should be running. Make sure your JobMonApp is running. else you can start it by ./jobmoninit..
See the post in this forum for exact syntax etc.
Hope this helps.
Lalitha
Hi,
I have a DataStage EE 7.5.1A installed on a Linux box. Whenever I issue the $DSHOME/bin/uv -admin -start command, I alway get two system messages. One is for the JobMobApp (has been brought up) and the other is for DataStage server (has been started). But I still get no color.
My problem is only running Parallel jobs don't get any color. So strange!?
I still couldn't figure out where and what should be modified for the Linux platform. However, I also have DataStage EE 7.5x2 on the Windows platform, I was having the same kind of problem, then I just reinstall the whole thing and the problem went away.
I have a DataStage EE 7.5.1A installed on a Linux box. Whenever I issue the $DSHOME/bin/uv -admin -start command, I alway get two system messages. One is for the JobMobApp (has been brought up) and the other is for DataStage server (has been started). But I still get no color.
My problem is only running Parallel jobs don't get any color. So strange!?
I still couldn't figure out where and what should be modified for the Linux platform. However, I also have DataStage EE 7.5x2 on the Windows platform, I was having the same kind of problem, then I just reinstall the whole thing and the problem went away.
-
- Participant
- Posts: 54607
- Joined: Wed Oct 23, 2002 10:52 pm
- Location: Sydney, Australia
- Contact:
I had this problem in our environment.vijayrc wrote:Figured it out after I posted...Works like a charm...Thanks anywayskumar_s wrote:Make sure the setting in adminstrator is turned on.
Parallel ---> Reporting ---> APT_NO_JOBMON --> FALSE
I have APT_NO_JOBMON set to false and started JobMonApp, now it is up and running.
But perforamnce statistics are not shown in my environment when I run PX jobs. Server jobs show fine. OS is solaris.
Appreciate If someone give the resolution who had the same issue.
Would there be any patch for this?
Thanks in advance.