I am facing some problem while calling a parallel job from a sequencer.
The paramter values that i pass to the job seqencer(Say X) is not being passed t o the parallel job While the job initiates(It passes something else Say Y).
So the parallel job and the sequencer aborted.
So i ran the parallel job individually with the required parameters(with X) and it ran fine.
After that i again ran the sequencer with the values i had first given(i.e. X). Now the parallel job got the values correctly( i.e X) and it runs fine.
My question is that does a parallel job caches the parameter values of last run? If so under what condition is it used ? Any project level setting for it ?
This is creating a big problem in the ST phase...
![Crying or Very sad :cry:](./images/smilies/icon_cry.gif)
The Datastage Version is 7.5.
Any pointers to it are welcome.
Thanks,