convertion of date DB2
Posted: Tue Jun 22, 2004 8:27 am
by auvray.muriel
Hello,
I start under PX.
I must extract from the data of a base DB2 with dates and stored in a dataset of which the structure is the same one as the table.
The problem is compared to the dates.
How then I convertr a date db2
my date : 12965 (2003-06-30)
I want : 2003-06-06 or 12965 (2003-06-30)
when I extract the data here is the message which I have :
Code: Select all
DB2_F1EWOPFT0,0: Invalid date value in setOutputFieldAsDate() for field '6' in output dataset '0'.
Date cannot be later than 9999-12-31 or earlier than 0001-01-03.
Julian days value = 1721423.
thank you for your help
Muriel
Re: convertion of date DB2
Posted: Wed Jun 23, 2004 1:24 am
by sanjay
use
iconv and oconv function
Dinesh
auvray.muriel wrote:Hello,
I start under PX.
I must extract from the data of a base DB2 with dates and stored in a dataset of which the structure is the same one as the table.
The problem is compared to the dates.
How then I convertr a date db2
my date : 12965 (2003-06-30)
I want : 2003-06-06 or 12965 (2003-06-30)
when I extract the data here is the message which I have :
Code: Select all
DB2_F1EWOPFT0,0: Invalid date value in setOutputFieldAsDate() for field '6' in output dataset '0'.
Date cannot be later than 9999-12-31 or earlier than 0001-01-03.
Julian days value = 1721423.
thank you for your help
Muriel
Posted: Wed Jun 23, 2004 11:14 am
by denzilsyb
Is that 'date' internal to AS400?
How do you know the value of 12965 is 2003-06-30? If this is how it is stored in DB2 then you need to get it out of there in the format you want.
I know that on Sybase IQ, we need to import a DATE column as CHAR/VARCHAR otherwise the date comes in completely wrong.
As far as I know, datastage has its own internal number for a date, and thats what sanjay is suggesting.
Once you get the DB2 date into datastage, then start with the iconv/ oconv functions.
From Help:
Iconv("1997 5 27", "D YMD") = 10740
Oconv(10740, "D YMD") = '1997 5 27'
Re: convertion of date DB2
Posted: Wed Jun 23, 2004 1:48 pm
by anandkumarm
auvray.muriel wrote:Hello,
I start under PX.
I must extract from the data of a base DB2 with dates and stored in a dataset of which the structure is the same one as the table.
The problem is compared to the dates.
How then I convertr a date db2
my date : 12965 (2003-06-30)
I want : 2003-06-06 or 12965 (2003-06-30)
when I extract the data here is the message which I have :
Code: Select all
DB2_F1EWOPFT0,0: Invalid date value in setOutputFieldAsDate() for field '6' in output dataset '0'.
Date cannot be later than 9999-12-31 or earlier than 0001-01-03.
Julian days value = 1721423.
thank you for your help
Muriel
I had a similar problem when my earliest date was 0001-01-01 I read the date as string and then changed internally and did all my computations.
Anand.
Posted: Wed Jun 23, 2004 11:24 pm
by richdhan
Hi Denzil and Sanjay,
Can we use IConv and OConv in parallel jobs. I don't think so.
What you say may be applicable to server jobs.
Thanks
Rich
db2 date datatype
Posted: Wed Jun 23, 2004 11:58 pm
by vikramarjula
In th DB2 database stage change the date datatype to string. From the output of that stage use a modify stage and use the timestamp_from_string or date_from_string (can look into the orchestrate manual) functions to convert to the timestamp/date datatype
Posted: Thu Jun 24, 2004 3:59 am
by denzilsyb
Hi Rich
lets put it this way - server jobs yes. Px Im not sure
![Embarassed :oops:](./images/smilies/icon_redface.gif)
. how do you compare dates in Px then?
Posted: Fri Jun 25, 2004 1:32 pm
by auvray.muriel
Thank you for your answers.
I chose the solution of vikramarjula.
I had another problem.
I had dates 0001-01-01. With the solution of vikramarjula, I can treat the data without problem
Bye
Muriel