Page 1 of 1

Parallel job run failed

Posted: Mon Nov 02, 2015 7:12 am
by sathishmca
Team,

I have installed 8.7 on windows server 2008 machine and i could create a server job and its ran fine. Parallel job troubles me while executing, it throws below meggaes for us to troubleshoot,


Contents of phantom output file
Unable to create new process. Will try again.
Create Process failed (3).

next message in Director:

Error setting up internal communications (fifo \\.\pipe\Training_LP-RT_SC3-CopyOfjb_test) STATUS() 2

Please help me in resolving this.

Thanks is advance.

Regards,
Sathish B

Posted: Mon Nov 02, 2015 12:38 pm
by PaulVL
In Unix world I would ask that you look at your user settings to see if nprocs was a tad on the low side for you.

I do not know what the equivalent is on Windows.