Hi,

I would like to know is it wise to have a set of parallel jobs being run by a server batch control job.

Your views will be much appreciated.
chulett
Charter Member
Charter Member
Posts: 43085
Joined: Tue Nov 12, 2002 4:34 pm
Location: Denver, CO

Post by chulett »

I don't see any issue and have done so without issue in the past. Do you have any specific concerns?
-craig

"You can never have too many knives" -- Logan Nine Fingers
ray.wurlod
Participant
Posts: 54607
Joined: Wed Oct 23, 2002 10:52 pm
Location: Sydney, Australia
Contact:

Post by ray.wurlod »

A job sequence (consisting solely of job activities linked one after the other) compiles to exactly the same Job Control routine as a Batch or user-written routine.
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
chulett
Charter Member
Charter Member
Posts: 43085
Joined: Tue Nov 12, 2002 4:34 pm
Location: Denver, CO

Post by chulett »

... and doesn't really know or care if the job it is running is Server or Parallel.
-craig

"You can never have too many knives" -- Logan Nine Fingers
piyu
Participant
Posts: 52
Joined: Thu Jul 21, 2005 12:22 am
Location: Singapore

Post by piyu »

Thanks all for your inputs. I had never done that before and hence wished to know the implications.