Running a sequence in a given time automatically

Posted: Tue Oct 20, 2009 9:09 am
by pklcnu
Hi All

Is it possible to run a sequence at a given time , is it possible to set the time so that the sequence runs automatically suppose say after the midnight ? If yes how to do this ?

Many Thanks

Posted: Tue Oct 20, 2009 9:11 am
by ArndW
From the Director you can, for any job, add it to the schedule by Select "Job" -> "Add to schedule". This is, by default, either Windows "AT" or UNIX "cron".

Posted: Tue Oct 20, 2009 9:11 am
by chulett
From Director, use the 'Add to schedule...' option. That will put it into cron and run it on whatever schedule you need.

Posted: Tue Oct 20, 2009 9:36 am
by pklcnu
chulett wrote:From Director, use the 'Add to schedule...' option. That will put it into cron and run it on whatever schedule you need. ...
Thanks very much indeed

Posted: Wed Oct 21, 2009 3:18 am
by chvenkat.v
if your problem is resolved then please make this topic as resolved... Smile