APT_CombinedOperatorController is taking more time to execut

Post questions here relative to DataStage Enterprise/PX Edition for such areas as Parallel job design, Parallel datasets, BuildOps, Wrappers, etc.

Moderators: chulett, rschirm, roy

Post Reply
babubino
Participant
Posts: 3
Joined: Fri Nov 28, 2008 5:51 am
Location: Hyderabad

APT_CombinedOperatorController is taking more time to execut

Post by babubino »

I have two different instances for a job in the same server.
For one instance
"APT_CombinedOperatorController,0: Operator completed. status: APT_StatusOk elapsed: 0.00 user: 0.00 sys: 0.00 (total CPU: 0.00)" it is taking 1 minute for execution,
whereas for other instance
"APT_CombinedOperatorController(0),0: Operator completed. status: APT_StatusOk elapsed: 273.47 user: 7.17 sys: 0.88 suser: 0.02 ssys: 1.29 (total CPU: 9.36)" it is taking 35 minutes for execution.

Can anybody let us know what is APT_CombinedOperatorController, why is the time difference between the two instances, and how can we tune this ?
babubino
bart12872
Participant
Posts: 82
Joined: Fri Jan 19, 2007 5:38 pm

Post by bart12872 »

APT_CombinedOperatorController group two or more process in an unique operator.

Does your two instance of the job treats a similar number of rows ?

Martin.
babubino
Participant
Posts: 3
Joined: Fri Nov 28, 2008 5:51 am
Location: Hyderabad

Post by babubino »

Hi Martin,

The number of rows for the instance which takes more amount of time is around 11,00,000 and for other instance 9,00,000

Binoop

bart12872 wrote:APT_CombinedOperatorController group two or more process in an unique operator.

Does your two instance of the job treats a similar number of rows ?

Martin.