Page 1 of 1

Juluan day Error

Posted: Fri Dec 12, 2008 5:15 am
by GJ_Stage
Hi Everybody,

I am getting the below error message while running my job.

APT_CombinedOperatorController,0: Fatal Error: Invalid Julian day

Someone tell me why it is coming?

Thanks in advance.

Posted: Fri Dec 12, 2008 12:25 pm
by ray.wurlod
No, because we have no idea at all of what your job design is attempting to do and because you have operator combination enabled which prevents you and us from determining which actual operator is throwing the error.

Re: Juluan day Error

Posted: Sat Dec 13, 2008 3:52 am
by Shruthi
If you are validations with date, the initial date value passed to that column is incorrect. This is one of the reasons for the error