Can User Variable Activity be Checkpointed?

Post questions here relative to DataStage Enterprise/PX Edition for such areas as Parallel job design, Parallel datasets, BuildOps, Wrappers, etc.

Moderators: chulett, rschirm, roy

Post Reply
Azzuri
Premium Member
Premium Member
Posts: 122
Joined: Tue May 13, 2008 11:42 am

Can User Variable Activity be Checkpointed?

Post by Azzuri »

There isn't a checkbox to indicate whether the activity can be checkpointed. I want the UserVariable Activity to be executed each time on a re-run (It's a restartable job). Any Ideas? It current skips the activity when restarting.
chulett
Charter Member
Charter Member
Posts: 43085
Joined: Tue Nov 12, 2002 4:34 pm
Location: Denver, CO

Post by chulett »

You mean there's no option to "do not checkpoint"... and you'd have to ask IBM why that is the case.
-craig

"You can never have too many knives" -- Logan Nine Fingers
ray.wurlod
Participant
Posts: 54607
Joined: Wed Oct 23, 2002 10:52 pm
Location: Sydney, Australia
Contact:

Post by ray.wurlod »

You just have to look at the abysmal way the GUI was written to answer that. How many other grids have you ever encountered with zero rows and you have to right click to create a row before you can use the grid?
:roll:
Sheesh
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.