Hi
I have a strange problem with version 8, windows environment.
i have a lot of sequences set to start at various timings of the day.
yesterday i rescheduled some off them, and this morning OTHER sequences had lost their schedule.
I have seen this once or twice before, but thought it was my mistake, but this time i am sure i did not touch any other sequences, neither did any one else.
Have any of you seen this strange behaviour before ?
regards
PT
job scheduling info lost when rescheduling other jobs
Moderators: chulett, rschirm, roy
-
- Premium Member
- Posts: 17
- Joined: Mon Dec 13, 2004 5:01 am
- Location: Denmark
- Contact:
-
- Participant
- Posts: 54607
- Joined: Wed Oct 23, 2002 10:52 pm
- Location: Sydney, Australia
- Contact:
Welcome aboard.
I have never seen this. Try looking at the DOS command AT before you change the schedule and again afterwards, to see whether you can discern what might be happening.
I suspect, though, that this will be one for your official support provider.
Hang on, does version 8 still use the AT scheduler, or something in Information Server/WebSphere? Further investigation is called for, unless someone who knows can post here.
I have never seen this. Try looking at the DOS command AT before you change the schedule and again afterwards, to see whether you can discern what might be happening.
I suspect, though, that this will be one for your official support provider.
Hang on, does version 8 still use the AT scheduler, or something in Information Server/WebSphere? Further investigation is called for, unless someone who knows can post here.
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.