Hi,
I have to run a sequencer for a set of files in a loop. So, i have the sequencer like this:-
Main sequencer:-
Start loop-->Job activity 1-->Job activity 2-->End loop
This sequencer loops for every file until all the files are processed.
Job activity 1 is a Job sequence which processes the data. Hence if this aborts while processing the file, it should trigger the Job Activity(which updates the table about the job status) and end loop until all the files are processed.
In Job activity 1, i have given the trigger as unconditional.
But, the problem is, if Job activity 1 aborts while processing the file, the whole sequencer aborts. Hence all the other files would not be processed until this error is rectified.My requirement is that the Job activity 2 should run after Job activity 1 even if it is aborted.
Can anyone help me in resolving this issue.
Sequencer logic
Moderators: chulett, rschirm, roy
-
- Participant
- Posts: 54607
- Joined: Wed Oct 23, 2002 10:52 pm
- Location: Sydney, Australia
- Contact:
Sequencer logic is easy. The output fires if "Any" of its inputs fires, or if "All" of its inputs fire.
What you have there is a job sequence, not a sequencer.
Your problem is that the job sequence is doing exactly what you have asked it to do, by checking "automatically handle failure" and not including explicit failure handling for Job Activity 1 or an Exception Handler.
What you have there is a job sequence, not a sequencer.
Your problem is that the job sequence is doing exactly what you have asked it to do, by checking "automatically handle failure" and not including explicit failure handling for Job Activity 1 or an Exception Handler.
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
-
- Participant
- Posts: 612
- Joined: Thu May 03, 2007 4:59 am
- Location: Melbourne
Re: Sequencer logic
And what all are the error handling options you have set / checked in your job parameter tab?
dnat wrote: In Job activity 1, i have given the trigger as unconditional.
But, the problem is, if Job activity 1 aborts while processing the file, the whole sequencer aborts.
Joshy George
<a href="http://www.linkedin.com/in/joshygeorge1" ><img src="http://www.linkedin.com/img/webpromo/bt ... _80x15.gif" width="80" height="15" border="0"></a>
<a href="http://www.linkedin.com/in/joshygeorge1" ><img src="http://www.linkedin.com/img/webpromo/bt ... _80x15.gif" width="80" height="15" border="0"></a>