Hi all,

I had tried it before, but out of curiosity, I went ahead and added both server and parallel jobs into the same Job Sequence. The sequence ran successfully.
Would you say it is not a good practice? Or is it forbidden to do it? :roll:
chulett
Charter Member
Charter Member
Posts: 43085
Joined: Tue Nov 12, 2002 4:34 pm
Location: Denver, CO

Post by chulett »

Or perfectly fine, as you've seen.