Hi,

Can any one let me know, is there any option to complie all the jobs in an DataStage project

Currently the version is 7.5.3
Naresh
sajidkp
Participant
Posts: 114
Joined: Thu Apr 30, 2009 12:17 am
Location: New Delhi

Post by sajidkp »

Hi,

Go to Tools in Designer

Tools-->Multiple Job Compile

Then Select whatever jobs you need to compile in the project.
Regards,
Sajid KP