Hi,
We are using DataStage 7.5.1 A Server Edition on Windows OS. The issue we have here is with the Job Seq. Suppose let's say we have 2 jobs in the sequence & we have enabled the trigger in the first job as "DS.JS = RUN OK OR DS.JS = RUN WARN" meaning if the first job finishes successfully or with warnings then run the second job of the sequence. This is not working in the sense even if firstjob aborts, datastage is exectuing the second job. Any ideas are welcome.
Thanks,
Sarat.
DataStage 7.5.1 A Server Edition Sequence Problem
Moderators: chulett, rschirm, roy
-
- Participant
- Posts: 26
- Joined: Fri Jul 13, 2007 6:33 am
-
- Participant
- Posts: 54607
- Joined: Wed Oct 23, 2002 10:52 pm
- Location: Sydney, Australia
- Contact:
Get the syntax correct by selecting activity variables and DS Constants from the Expression Editor operand menu.
Code: Select all
JobActivity1.$JobStatus = DSJS.RUNOK Or JobActivity1.$JobStatus = DSJS.RUNWARN
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.