HI,
can any one help in this issue,
the sequencer is failed due to this error.
Controller problem and Error calling DSRunJob(code=-14)
[Timed out while waiting for an event]
Thanks in advance
Controller problem and Error calling DSRunJob(code=-14)
Moderators: chulett, rschirm, roy
-
- Participant
- Posts: 54607
- Joined: Wed Oct 23, 2002 10:52 pm
- Location: Sydney, Australia
- Contact:
-
- Premium Member
- Posts: 32
- Joined: Fri Sep 26, 2003 3:45 am
Avoid Using Sequencer Stage
Hi,
This is due to overlaod in the server. Your job sequencer can avoid this by limiting the number of jobs that are running in parallel. Say you are running 10 jobs in parallel, then you can split them into two sets of five jobs each with a sequencer stage in between two sets.
This is due to overlaod in the server. Your job sequencer can avoid this by limiting the number of jobs that are running in parallel. Say you are running 10 jobs in parallel, then you can split them into two sets of five jobs each with a sequencer stage in between two sets.
Re: Avoid Using Sequencer Stage
thanks alot for the informationmandyli wrote:Hi,
This is due to overlaod in the server. Your job sequencer can avoid this by limiting the number of jobs that are running in parallel. Say you are running 10 jobs in parallel, then you can split them into two sets of five jobs each with a sequencer stage in between two sets.