Hi
we are using Job sequencer in the our project. I would like to know about
"do not check point" option in the Job activity window.
Can you please any one give some idea?
Thanks
Man
Job sequence issue
Moderators: chulett, rschirm, roy
-
- Participant
- Posts: 54607
- Joined: Wed Oct 23, 2002 10:52 pm
- Location: Sydney, Australia
- Contact:
-
- Participant
- Posts: 42
- Joined: Mon Apr 21, 2008 1:49 am
Re: Job sequence issue
"do not check point"
Check points are used during run time of sequencer. If say fifth job in the sequencer fails and you want to start the sequencer from the point where it is failed then u should give "Check Point"
If u dont want this to happen and start the sequencer from the first job then u need not check it
Check points are used during run time of sequencer. If say fifth job in the sequencer fails and you want to start the sequencer from the point where it is failed then u should give "Check Point"
If u dont want this to happen and start the sequencer from the first job then u need not check it
Re: Job sequence issue
The checkpoint property on job sequences allows a sequence to be restarted at the failed point.-------------------------------------------------------------------------------
Each sequence needs it own log or the log becomes too difficult to follow. The solution is to create a generic Sequence Job Check routine in DataStage BASIC/OSH that is run after every child sequence finishes. It retrieves all the warning and error messages from that child sequence and displays them in the parent sequence with the child job name as a prefix to the message. In previous projects I have used this technique to capture and email messages to support users
:D
Each sequence needs it own log or the log becomes too difficult to follow. The solution is to create a generic Sequence Job Check routine in DataStage BASIC/OSH that is run after every child sequence finishes. It retrieves all the warning and error messages from that child sequence and displays them in the parent sequence with the child job name as a prefix to the message. In previous projects I have used this technique to capture and email messages to support users
:D
mandyli wrote:Hi
we are using Job sequencer in the our project. I would like to know about
"do not check point" option in the Job activity window.
Can you please any one give some idea?
Thanks
Man
Re: Job sequence issue
hi,
ans for ur que is (you r using jobsequencer in that u have 5 jobactivities if the job aborted after 4 job u can run from 4 onwards but if u want to run again from 1job or 2 job then u have to enable that option then the sequencer will run again from wher u required)
regards,
sudheer
ans for ur que is (you r using jobsequencer in that u have 5 jobactivities if the job aborted after 4 job u can run from 4 onwards but if u want to run again from 1job or 2 job then u have to enable that option then the sequencer will run again from wher u required)
regards,
sudheer
Thanks,
Madhavi
Madhavi
-
- Participant
- Posts: 54607
- Joined: Wed Oct 23, 2002 10:52 pm
- Location: Sydney, Australia
- Contact:
Sudheer, please strive for a professional standard of written English expression on DSXchange. In particular do not use SMS-style abbreviations. DSXchange is not a mobile telephony device, and such abbreviations make the already burdensome task of understanding English even more difficult for those whose first language is not English.
Even as a proficient native language speaker of English I found your post rather incomprehensible.
Even as a proficient native language speaker of English I found your post rather incomprehensible.
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
Re: Job sequence issue
Good Lord, do you send emails at work that look like this? Is this really how you want to represent yourself as a professional on a world-wide user support forum?madhavi83 wrote:ans for ur que is (you r using jobsequencer in that u have 5 jobactivities if the job aborted after 4 job u can run from 4 onwards but if u want to run again from 1job or 2 job then u have to enable that option then the sequencer will run again from wher u required)
![Confused :?](./images/smilies/icon_confused.gif)
-craig
"You can never have too many knives" -- Logan Nine Fingers
"You can never have too many knives" -- Logan Nine Fingers