how we will identify how many partions are there in our job

Post questions here relative to DataStage Enterprise/PX Edition for such areas as Parallel job design, Parallel datasets, BuildOps, Wrappers, etc.

Moderators: chulett, rschirm, roy

Post Reply
kmuralikrishna
Participant
Posts: 2
Joined: Fri Nov 23, 2007 1:00 am

how we will identify how many partions are there in our job

Post by kmuralikrishna »

Hi,
How can we identify the how many partions are there in a parallel job
Maveric
Participant
Posts: 388
Joined: Tue Mar 13, 2007 1:28 am

Post by Maveric »

Based on the number of nodes present in the configuration file that is used to run the job.
ray.wurlod
Participant
Posts: 54607
Joined: Wed Oct 23, 2002 10:52 pm
Location: Sydney, Australia
Contact:

Post by ray.wurlod »

Welcome aboard.

The only certain way is to inspect the score.

Monitor view in Director can also reveal this information.

It may be different for different stages.

When's the interview?
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
Govindarajan
Participant
Posts: 24
Joined: Mon Jul 12, 2004 10:16 am

Post by Govindarajan »

Eventhough if you have 4 or 8 node configuration, the DS may or may not use all nodes. So the only correct option is to check the monitor while running the job. it shows as stage X 2 or StageX4 etc