Running the job on 5thBusinessday of every month

Post questions here relative to DataStage Enterprise/PX Edition for such areas as Parallel job design, Parallel datasets, BuildOps, Wrappers, etc.

Moderators: chulett, rschirm, roy

Post Reply
scorpion
Participant
Posts: 144
Joined: Thu May 12, 2005 4:19 am

Running the job on 5thBusinessday of every month

Post by scorpion »

Hi All,

I have a requirement to generate a sequential file from sql server database and it is a parallel job.

And we are using Autosys to schedule and run our datastage jobs.

But for this perticular file,the requirement is like:

it should generate(datastage job should run) only on 5th bussiness day/5th working day of the every month.

i.e the datastage job is to be scheduled in Autosys on every Fifth working day of the month at 09:30GMT hrs i.e. 05/10/2007, 07/11/2007,07/12/2007 ETC..

How should i approach this?Does any one came across rqrmnt like this?

Help should be appreciated..


thanks in advance..
Thanx&Regards
scorpion
chulett
Charter Member
Charter Member
Posts: 43085
Joined: Tue Nov 12, 2002 4:34 pm
Location: Denver, CO

Post by chulett »

You don't approach this at all, in my opinion. You hand this requirement to your AutoSys folks and tell them when it needs to run. Their problem, not yours.
-craig

"You can never have too many knives" -- Logan Nine Fingers