Page 1 of 1

datastage scheduler running jobs one hour prior to the sched

Posted: Mon Mar 16, 2015 5:41 am
by shahidbakshi
Hi experts,

Datastage parallel jobs are running one hour prior to the job schedule from the director.
Recently we have changed the timezone from MESZ to MES timezone. DS services are restarted also but still we see jobs running one hour prior to the job schedule.
Could you please share your advise/suggestions.

Does DS.REINDEX ALL help resolve this issue?

Version: DS 11.3x , AIX platform. Client windows 2008 R2.

Appreciate any help.

Thanks
Shahid

Posted: Mon Mar 16, 2015 3:19 pm
by ray.wurlod
I'd be looking at the scheduling service exposed by the application server, to check whether its timezone environment variable (or explicit setting) is correct.

Posted: Tue Mar 17, 2015 7:15 am
by chulett
So nowadays that's not cron I take it?

Posted: Tue Mar 17, 2015 11:57 am
by qt_ky
My 11.3.1 still uses crontab...

One internet search suggests to restart the cron service after making changes to TZ (timezone). Talk to your UNIX Admin.

Re: datastage scheduler running jobs one hour prior to the s

Posted: Tue Mar 17, 2015 1:35 pm
by AshishDevassy
Did you check the time on the Infosphere Server ?
Restarting services wont help unless the server times are updated as well.