Page 1 of 1

Datastage 7x to 11x

Posted: Thu Nov 27, 2014 2:36 am
by karthi_gana
All,

is it possible to upgrade Datastage 7.5 version to Datastage 11.1 directly?

I heard we can't move like that. First we have to migrate the jobs to 8x version and then 8X job needs to be migrated to 11x.

Inputs are welcome!

Posted: Thu Nov 27, 2014 6:01 am
by qt_ky

Posted: Thu Nov 27, 2014 6:04 am
by qt_ky
I have not heard that before.

I would think you install and configure the newest release, then export each old project and import into each new project.

Here are a few links for you to research.

Migrating from InfoSphere DataStage

Posted: Thu Nov 27, 2014 8:14 am
by priyadarshikunal
did you try upgrading directly? From what I recollect, pre-7.5 is not directly supported and for that you need to move to 7.5 and then to higher versions.

Will have to wait and see if anyone has some experience doing that. But I doubt if it be answered before monday due to holidays.

Is it 11.3 or 9.1? as you have mentioned 11.1


and yes, you still may need to change a few stages which are not supported in 11.3 for example ABAP CPI-C

Posted: Fri Dec 12, 2014 11:17 am
by karthi_gana
11.3 only.

Posted: Sat Dec 13, 2014 12:33 pm
by priyadarshikunal
You should be good for direct upgrade apart from the things I mentioned there.

Posted: Sat Dec 13, 2014 12:50 pm
by priyadarshikunal
This link gives some detail about the tasks. Although its for old version, i think it stll holds good.

Posted: Fri Dec 19, 2014 12:04 pm
by kkeigley
Thank you, this was very helpful.

Posted: Mon Dec 22, 2014 2:57 am
by boolseye
Hi, I would suggest ( if you have the access to newest version then) try to export few jobs from 7.5 and import in 11.
We recently migrated lots of jobs from 7.5, 8.1 to version 9.