Half Parallel and Half server jobs

Posted: Wed May 25, 2011 10:00 am
by Poornimayvs
Hi all,

Can we have half project in server jobs and half project in parallel jobs? I checked in Google and found mixed answers for this. Please let me know if any one knows.

Thanks.

Posted: Wed May 25, 2011 10:14 am
by Ravi.K
You could use both server and Parallel jobs in same project.

Posted: Wed May 25, 2011 10:37 am
by pandeesh
Is it possible to call few server jobs and few parallel jobs in a job sequence?

Thanks

Posted: Wed May 25, 2011 10:48 am
by DSguru2B
Yes.

Posted: Thu May 26, 2011 12:27 am
by singhald
in one project you can both server and parallel jobs. people uses both type of canvas to develop jobs based on their requirements. in sequencer you can call both types of job along with other actvities.