Referenced Shared Container has been modified

A forum for discussing DataStage<sup>®</sup> basics. If you're not sure where your question goes, start here.

Moderators: chulett, rschirm, roy

Post Reply
deepa_shenoy
Participant
Posts: 95
Joined: Thu Sep 24, 2009 12:15 am
Location: India

Referenced Shared Container has been modified

Post by deepa_shenoy »

Hi,

I have imported a job created in DataStage 7.5 to DataStage 8.1. This job has a number of Shared Containers.

I modified two of the Shared Containers and compiled the job. The job got compiled successfully, but when I try to run the job, from the designer, it says 'Referenced Shared Container has been modified'.

What could be the issue and how can this be resolved?

Thanks in advance.

-Deepa
tennetiharika
Participant
Posts: 11
Joined: Mon Feb 25, 2008 5:53 am
Location: Hyderabad

Re: Referenced Shared Container has been modified

Post by tennetiharika »

deepa_shenoy wrote:Hi,

I have imported a job created in DataStage 7.5 to DataStage 8.1. This job has a number of Shared Containers.

I modified two of the Shared Containers and compiled the job. The job got compiled successfully, but when I try to run the job, from the designer, it says 'Referenced Shared Container has been modified'.

What could be the issue and how can this be resolved?

Thanks in advance.

-Deepa
call the changed shared container again and run the job.try it out , should work
___________________
Regards,
Harika


I Have not failed.I have found 10,000 ways that won't work-Thomas Edison
Post Reply