tanaya.deshpande@tieto.co wrote:Is there any activity to forcefully stop the sequence
Terminator.

Posted: Thu Mar 31, 2011 7:24 am
by tanaya.deshpande@tieto.co
What I have done is I have used a sequencerstage all the job activities connect to sequencer (via failed link) and the sequencer connects to the loop stage I have set 'Any' in the sequencer...and the sequencer connects to loop activity ...

Now whnever any of the job activity fails the sequencer directs to the loop ..

what do u think ???

Posted: Thu Mar 31, 2011 7:28 am
by chulett
How are you getting out of the loop when they all succeed?

Posted: Thu Mar 31, 2011 9:15 pm
by tanaya.deshpande@tieto.co
if they all succeed it never enters the loop it will enter the loop only if any of the job fails..