parallel jobs with warning
Moderators: chulett, rschirm, roy
-
- Participant
- Posts: 8
- Joined: Fri Oct 26, 2012 8:05 am
parallel jobs with warning
I have a parallel jobs with warning
but when those jobs are run in a sequence job the sequence job is aborted
I want to know what is the option in the sequence job to run with the warninigs of parallel jobs
thanks
but when those jobs are run in a sequence job the sequence job is aborted
I want to know what is the option in the sequence job to run with the warninigs of parallel jobs
thanks
-
- Participant
- Posts: 8
- Joined: Fri Oct 26, 2012 8:05 am
parallel jobs with warning
if I have a parallel job has over 50 warinings in that case I should do with the job sequence
-
- Participant
- Posts: 8
- Joined: Fri Oct 26, 2012 8:05 am
parallel jobs with warning
how I can make the choice to deprecate the informational warning. ?
please
please
-
- Participant
- Posts: 96
- Joined: Mon May 14, 2012 1:30 pm
Hi ashidalgov
do you mean the job activity which calls the job itself- that fails ?
Or the complete sequence fails if that job is finished with warnings.
for the former case, you already have the above suggestions.
for the later one, you probably need to make sure the trigger to the next activity is correctly defined(by defining Custom = OK or Finished with warnings)
do you mean the job activity which calls the job itself- that fails ?
Or the complete sequence fails if that job is finished with warnings.
for the former case, you already have the above suggestions.
for the later one, you probably need to make sure the trigger to the next activity is correctly defined(by defining Custom = OK or Finished with warnings)
Rgds,
MB
MB