I have three flows in a job:
1) MQ1->Transformer1->Sequential file1
2) MQ2->Transformer2->Sequential file2
3) MQ3->Transformer2->Sequential file3
My requirement is run 1), 2) and 3) in the sequential order. Run 1) and go to 2) only if 1) finishes and go to 3), only when 1) and 2) finishes. If they fail in the order, the job should fail altogether.
Please advise
Running flows in a job in sequential order
Moderators: chulett, rschirm, roy
Basically, this:
Perhaps read from a known empty file so that nothing is written to MQ but rather just serves as a process break...
Still think they should be three separate jobs, control the order and what happens when any given one fails by using a Sequence job.
Code: Select all
MQ1->Transformer1->SequentialFile1->MQ2->Transformer2->SequentialFile2->MQ3->Transformer3->SequentialFile3
Still think they should be three separate jobs, control the order and what happens when any given one fails by using a Sequence job.
-craig
"You can never have too many knives" -- Logan Nine Fingers