hi all,
I have a question to ask in DATASTAGE. I have an control job which controls around 20 jobs. Therefore if for some reason the job (say 15th) gives an error. then i need to rerun the control job all over again from job1.
Is there any shortcut by which say I can restart the job after the 14th job.
Regards,
Vivek
Posted: Fri Jun 08, 2001 1:06 pm
by admin
I use a parm called startgroup and set to the job I want to restart at,
startOK = @FALSE
If startgroup = "group1" Then
startOK = @TRUE
job control statements for job 1
End ;* end of group1
If startgroup = "group2" OR startOK Then
startOK = @TRUE
job control statements for job 2
End ;* end of group2
"Vivek Pandey."
informix-datastage@oliver.com
cc: (bcc: Art Rubright/NYLIC)
06/08/2001 08:37 Subject: CONTROL JOB
AM
Please respond
to
informix-datasta
ge
hi all,
I have a question to ask in DATASTAGE. I have an control job which controls around 20 jobs. Therefore if for some reason the job (say 15th) gives an error. then i need to rerun the control job all over again from job1.
Is there any shortcut by which say I can restart the job after the 14th job.
Regards,
Vivek
Posted: Fri Jun 08, 2001 8:33 pm
by admin
Yes, it involves writing job control code with more "intelligent" sensing and restart capability, typically recording (in a table or O/S file) where each run gets up to. I am aware of a number of sites doing exactly this. One of these has a four level job control hierarchy with row count reconciliation, full restart capability, and much more. Their secret was planning what they wanted to do before implementing it in DataStage BASIC.
-----Original Message-----
From: Vivek Pandey. [mailto:
vive@sonata-software.com]
Sent: Friday, 08 June 2001 22:38
To:
informix-datastage@oliver.com
Subject: CONTROL JOB
hi all,
I have a question to ask in DATASTAGE. I have an control job which controls around 20 jobs. Therefore if for some reason the job (say 15th) gives an error. then i need to rerun the control job all over again from job1.
Is there any shortcut by which say I can restart the job after the 14th job.
Regards,
Vivek
Posted: Fri Jun 08, 2001 9:39 pm
by admin
Does this type of job control require the QA module, or does the QA module just make this level of JC easier to implement & manage?
-----Original Message-----
From: Ray Wurlod [mailto:
ray.wurlod@Informix.Com]
Sent: Friday, June 08, 2001 3:34 PM
To:
informix-datastage@oliver.com
Subject: RE: CONTROL JOB
Yes, it involves writing job control code with more "intelligent" sensing and restart capability, typically recording (in a table or O/S file) where each run gets up to. I am aware of a number of sites doing exactly this. One of these has a four level job control hierarchy with row count reconciliation, full restart capability, and much more. Their secret was planning what they wanted to do before implementing it in DataStage BASIC.
-----Original Message-----
From: Vivek Pandey. [mailto:
vive@sonata-software.com]
Sent: Friday, 08 June 2001 22:38
To:
informix-datastage@oliver.com
Subject: CONTROL JOB
hi all,
I have a question to ask in DATASTAGE. I have an control job which controls around 20 jobs. Therefore if for some reason the job (say 15th) gives an error. then i need to rerun the control job all over again from job1.
Is there any shortcut by which say I can restart the job after the 14th job.
Regards,
Vivek
Posted: Fri Jun 08, 2001 10:14 pm
by admin
It does not require any module. In fact, the multi-level hierarchy was originally implemented in DataStage 2.2, well before source control and other add-ons appeared. (I take it thats what you mean by "the QA module")
-----Original Message-----
From: David Daugherty [mailto:
DDaugherty@pilgrimspride.com]
Sent: Saturday, 09 June 2001 07:40
To:
informix-datastage@oliver.com
Subject: RE: CONTROL JOB
Does this type of job control require the QA module, or does the QA module just make this level of JC easier to implement & manage?