Page 1 of 1

View log

Posted: Wed Mar 08, 2006 10:28 am
by meena
Hi All,
I want to view log for 20 th feb. Is it possible to go back and view the previous date logs.

with regards,
Meena

Posted: Wed Mar 08, 2006 11:02 am
by I_Server_Whale
Yes. It is if you are not auto-purging the log entries.

What is the auto-purge setting for your project? You can get this information from the 'Administrator'.

Thanks,
Naveen.

Posted: Wed Mar 08, 2006 11:05 am
by mauherga
Hi meena,

It is posible if your DS configuracion for that job doesn't delete yet the log of the job. In DS Director go to the log of the job do you want, then right click and select "filter", then select "older" and "last" in limit section. This will show you all de logs for that job. You can filter most especificaly using this window.

I hope this can help you.

Posted: Wed Mar 08, 2006 12:01 pm
by narasimha
If the logs are cleared/purged according to the setting or intensionally, there is no way to get it back.
If you forsee such requirement to see previous days/jobs run logs you have to set the Auto purge options to a high number
I guess the maximum allowed is 99 days or 99 job runs through the DS GUI