Job Sequence

Posted: Wed Feb 15, 2006 11:19 am
by reddy
Hi Guys,

I have a Job sequence running daily with 10 jobs but from tomorrow onwards i need to stop running one of the job in this job sequence.

How do i make one of the job as non runnable state.

Thanks in advance.

Reddy

Posted: Wed Feb 15, 2006 11:44 am
by ArndW
Rename it.

Posted: Wed Feb 15, 2006 11:54 am
by reddy
Hi Andrew,

just for few days i don't want to run the particular job, i need that job from monday onwards.

I have an idea, why don't i change the job execution action from run to
validate only.

Can you please make sure is this correct or not.

Thanks
Reddy

Posted: Wed Feb 15, 2006 11:57 am
by ArndW
If your job validates correctly then that should work as well.