Hi guys,
I am stuck in a situation right now. i built a sequencer with three jobs in it
J1 --> J2 ---> J3.
they run sequentially upon the successfull completion of its predecessor.
From each of these job activites i have a link going to a sequencer stage specifed to 'Any'. The sequencer is then connected to a terminator activity.
Each of these links going to the squencer are set to trigger 'otherwise'.
My basic purpose is to abort the sequence even any job activity finishes with warnings.
The problem is that the job is restartable. Say J2 got finished with warninings, the trigger fired and led the execution stream to the terminator activity. i go in fix the job and re-run the squence, again it goes down the exact same path as before, i.e, to the terminator. it has to re-run J2 but instead its skipping it.
how do i tackle that.?
I am stuck in a situation right now. i built a sequencer with three jobs in it
J1 --> J2 ---> J3.
they run sequentially upon the successfull completion of its predecessor.
From each of these job activites i have a link going to a sequencer stage specifed to 'Any'. The sequencer is then connected to a terminator activity.
Each of these links going to the squencer are set to trigger 'otherwise'.
My basic purpose is to abort the sequence even any job activity finishes with warnings.
The problem is that the job is restartable. Say J2 got finished with warninings, the trigger fired and led the execution stream to the terminator activity. i go in fix the job and re-run the squence, again it goes down the exact same path as before, i.e, to the terminator. it has to re-run J2 but instead its skipping it.
how do i tackle that.?