question about qualitystage
Posted: Wed May 25, 2005 9:18 am
by MukundShastri
Hi,
We have not used quality stage . Hence following basic question about the same.
We want to use do data cleansing using difference business rules of around 460 sequential files. For each file in input we should have one file in output after cleasing.
Does qualitystage has the template job facility which is available in enterprise edition parallel jobs. All the files have same metadata. Can one template job of Quality stage handle different input files and different cleaning rules dynamically.
How difficult it will be to create such jobs. How much efforts do you estimate to do that roughly?
Thanks
Mukund
Re: question about qualitystage
Posted: Wed May 25, 2005 10:39 am
by ram1899
Mukund;
Quality stage is whole diffrent from Enterprise Edition and Job you need to develope in in Quality stage Env
In Quality Stage you have four steps to do
Investigate
Standardize
Match
Survive
If you are saying biffrent business rule for diffrent seq file than I think you need diffrent Jobs form them
You can create Standardize , Match and Survive Jobs for one Seq file If you could attain the correct output as per your Requirment
All you need to do is copy same Job for Diffrent Seq file Change Input file Name and Intermediate files you are creating and Output file names
And you need to apply diffrent Business rules for each Seq file
The first set of Jobs will act a Job Templets for you
Im' still bit busy I give this solution in hurry and please try to understand it
If I can get back to it I will tell you more in Detail
Thank oyu
MukundShastri wrote:Hi,
We have not used quality stage . Hence following basic question about the same.
We want to use do data cleansing using difference business rules of around 460 sequential files. For each file in input we should have one file in output after cleasing.
Does qualitystage has the template job facility which is available in enterprise edition parallel jobs. All the files have same metadata. Can one template job of Quality stage handle different input files and different cleaning rules dynamically.
How difficult it will be to create such jobs. How much efforts do you estimate to do that roughly?
Thanks
Mukund
Posted: Wed May 25, 2005 12:23 pm
by MukundShastri
Thanks for the Reply.
Can we integrate QualityStage with Enterprise edition ?
If I want to create input file -->cleansing rule ---> output file kind of job, how much time it should take. In datastage such job should take max half day with testing.
Your inputs will be appreciated.
Thanks
Mukund
Posted: Wed May 25, 2005 6:38 pm
by ranga1970
when so comfortable with DS why do want to use QS, as ram said its whole different env and it whilly depends on you skills about the time frame, and this post should have been in whole different forum......
Posted: Thu May 26, 2005 6:54 am
by ram1899
Fine do it in DataStage ( Save some money for your client ) if DS is going to Do what you want then take out QS don't bring it in and there is will be other headaches as you need to Calll this QS Jobs ( QS Scripts from in DS Sequncer so the it runs before running the your DS Job)
Mukund if you can do it DS in half Day don't think of using QS
Thank you
MukundShastri wrote:Thanks for the Reply.
Can we integrate QualityStage with Enterprise edition ?
If I want to create input file -->cleansing rule ---> output file kind of job, how much time it should take. In datastage such job should take max half day with testing.
Your inputs will be appreciated.
Thanks
Mukund
Posted: Thu May 26, 2005 7:26 am
by ray.wurlod
QualityStage is the right tool for the job that it does; standardizing and cleaning data.
It can be called from DataStage jobs using the QualityStage plug-in stage; however, the QualityStage jobs must have been designed and tested first.
Posted: Thu May 26, 2005 11:05 am
by ram1899
Ray
Youy are correct it is very good tool when we need to standardizing and cleaning the data
Mukund was telling that he can do the same in 1/2 day ( If you have Good Knowledge of QS you can do the Same in 1/2 day ) As his file are having same Meta Data if he developes the QS jobs for one file it will be cake walk for him to do the 400+
Mukund try to USE QS you will love it
Thank you
Ram-
ray.wurlod wrote:QualityStage is the right tool for the job that it does; standardizing and cleaning data.
It can be called from DataStage jobs using the QualityStage plug-in stage; however, the QualityStage jobs must have been designed and tested first.