Is Copying of stages from one job to other job not possible in DS 7.0.

When i tried this, it was not possible. But i tried to copy in the same job it happened.


In DS 7.1, this was possible , but in DS 7.0, it was not possible.


Is it possible in DS 7.0

Posted: Tue Nov 30, 2004 8:47 am
by chand
Hi nkln@you,


As per my knowledge containers are reused from on job to another job & a stage cannot be copied and used in another job.

Posted: Tue Nov 30, 2004 8:51 am
by chulett
Yes, it is possible. One of the very nice things they finally added in the 7.x versions was copy and paste, which means you can copy a stage in one job and paste it into another. I'm running 7.0.1 right now and do it all the time.

The other ong-awaited big winner was allowing 'dangling links'. :D

Posted: Tue Nov 30, 2004 3:41 pm
by vmcburney
Are you attempting to copy stages between jobs in seperate Designer sessions? You can only copy stages inside the one Designer. This should work in version 7.0.

Posted: Tue Nov 30, 2004 3:51 pm
by chulett
No, you can copy across multiple Designer sessions. Just did. :wink:

Posted: Tue Nov 30, 2004 11:59 pm
by nkln@you
Thanks for your replies, but i should say sorry because ,i tried to copy a routine activity of a sequencer job into a server job. This is the mistake i did. So, i did'nt get copied. Immediately without checking the jobs , i posted this :?


Otherwise, we can copy between two DS sessions also, if the jobs are of same type.


Thanks once again.