You may need to check whether the scheduled runs are supposed to run as a particular user. You do this from the DataStage Administrator, Project Propreties, Scheduled Runs tab.
By default, this is left blank (so everything runs as the system scheduler). If a particular value for the username&password is set there, those credentials will be used to run the jobs/batches.