Job control process (pid 26562) has failed

Posted: Thu Feb 02, 2012 12:29 am
by esivaprasad
Hi,
when we are running our main sequence (in this total 1375 jobs), some jobs are failing with the error
Job control process (pid 26562) has failed .
ie Job control process (pid xxxxx) has failed.
due to some jobs failing with this error,our daily load not completing.
if we ran the failure jobs,its completing successfully.
can you please any one help me how to resolve this Job control process (pid xxxxx)has failed, these errors.

Posted: Thu Feb 02, 2012 3:58 am
by kandyshandy
I have faced this in the past and just a rerun would resolve the problem. If interested, you can take it to IBM support.

Posted: Thu Feb 02, 2012 8:03 am
by chulett
When you reset the Aborted job, is a "From previous run..." entry added to the job's log? If so, please post the contents.

Posted: Thu Feb 02, 2012 3:02 pm
by ray.wurlod
This error usually occurs if the controlling process (sequence, process running dsjob, job executing DSRunJob, etc.) is killed or if connection between the node and the conductor is lost for any reason. This is why a re-run is usually successful - the interruption does not occur the second time. They have the annoying property of being intermittent faults.