Job completed in designer but its still running in director

Posted: Tue Jun 21, 2011 3:37 pm
by just4u_sharath
Hii,
I have an issue with a job. Its shows that the job is completed in designer(green) but still shows its running in director. The after job sub routine also got executed the file got zipped. Ideally the job finises in 4 hours but now its taking 11 hours from yesterday

Posted: Tue Jun 21, 2011 4:39 pm
by ray.wurlod
Are there any warnings in the job log? Is there a "Finished" event in the job log?