Page 1 of 1

Automate Converting OCI 8 to OCI 9

Posted: Thu Feb 11, 2010 1:04 am
by suresh.narasimha
Hi All

There is a need to convert all the OCI 8 stages in a project to OCI 9.

The process we followed was, exported a job in XML format and replaced the Stage Type from "ORACI8" to "ORACI9" and the code worked.

Is there a better way to convert the stages?? Like any command from Administrator to do it


Thanks,
Suresh

Re: Automate Converting OCI 8 to OCI 9

Posted: Thu Feb 11, 2010 4:59 am
by sachin1
Hi Suresh,
i just have information regarding an utility OCI8TO9.B, which converts your oracle oci8 stage to oracle 9i OCI stage, but never tried it.

please check out on more details on OCI8TO9.B utility.

Posted: Thu Feb 11, 2010 7:10 am
by chulett
Exactly. IBM / Ascential provides a utility to do that for you automagically.

Posted: Thu Feb 25, 2010 10:28 pm
by nwexler
Right, however if you do move to 8.x the utility won't work (eCase 125155). You'll need to use the utility in 7.x then migrate.