Page 1 of 1

Error calling subroutine:DSR_SCHEDULE (Action=3);

Posted: Thu Oct 25, 2007 12:53 am
by ICE
Dear All,

Is there any idea to solve the following error msg?
Error calling subroutine:DSR_SCHEDULE (Action=3); check DataStage is set up correctly in project Prj1 [Subroutine failed to complete successfully [30107]]
New jobs those I gave schedule on last 3 days ago cannot run in schedule. I have to reschedule it. But the old job still running in schedule. But I cannot check the schedule time. Whenever I tried to check the schedule time, I got that error msg and cannot see any schedule although the schedule window was open.


Thanks,

Re: Error calling subroutine:DSR_SCHEDULE (Action=3);

Posted: Wed Oct 31, 2007 4:51 am
by ICE
Dear All,

I still got this error msg and cannot see any schedule. Is there anybody can help me to see the schedule please???

Now I cannot see the schedule and cannot do reschedule.

Help me please...... :(

Thanks in advance,
ICE

ICE wrote:Dear All,

Is there any idea to solve the following error msg?
Error calling subroutine:DSR_SCHEDULE (Action=3); check DataStage is set up correctly in project Prj1 [Subroutine failed to complete successfully [30107]]
New jobs those I gave schedule on last 3 days ago cannot run in schedule. I have to reschedule it. But the old job still running in schedule. But I cannot check the schedule time. Whenever I tried to check the schedule time, I got that error msg and cannot see any schedule although the schedule window was open.


Thanks,

Re: Error calling subroutine:DSR_SCHEDULE (Action=3);

Posted: Wed Oct 31, 2007 5:45 am
by ogmios
my hunch would be that you have access rights problems in your project directory. Are you using the same userid now as you were using before?

In any case, a schedule for a job (when done from the GUI and not with dsjob) consists of 2 pieces: some small piece in your project itself and the part in the OS scheduler.

You could try to export/import/recompile the job and try to reschedule it.

Posted: Wed Oct 31, 2007 6:04 am
by ray.wurlod
What happens when you open a cmd shell and type the AT command?

Re: Error calling subroutine:DSR_SCHEDULE (Action=3);

Posted: Wed Oct 31, 2007 7:44 pm
by ICE
Dear ogmios,

I use the same user id as before.
I could not see any job scheduler. Whenever I try to open the scheduler, I got that msg and can see nothing inside except job name and no schedule status.
But the jobs are running in still running in schedule. But I cannot see the schedule and hence cannot unschedule or reschedule :(
In previous days, I encounter many problem with DS jobs because of the disk space problem. Some of the jobs corrupted. After I solve the disk space problem, I import the backup jobs for the corrupted job. Now all the jobs are running properly except this scheduler. I don't know how to recover this schedule. The problem may be because of that because I got this error msg since at that time.
Is there any idea you have???

Thank you so much for your help,
ICE



ogmios wrote:my hunch would be that you have access rights problems in your project directory. Are you using the same userid now as you were using before?

In any case, a schedule for a job (when done from the GUI and not with dsjob) consists of 2 pieces: some small piece in your project itself and the part in the OS scheduler.

You could try to export/import/recompile the job and try to reschedule it.

Posted: Wed Oct 31, 2007 7:57 pm
by ICE
Dear Ray,

When I type AT command, I see as below.

C:\Documents and Settings\sdserver>at
Status ID Day Time Command Line
-------------------------------------------------------------------------------
1 Each M T W Th F S Su 12:05 PM D:\DWDEV\SCHEDULE.BAT
582 Each M T W Th F S Su 9:00 AM vmdsr_sched.exe C:\ARDENT\DATASTAGE\PROJECTS\REPORTS 308 0/0 2

Before this, I saw a lot of schedule in windows scheduler but now I saw only 2 jobs for DS jobs. But all the scheduler jobs are still running in schedule.
May I know how to recover it???
Is it the reason of my previous problems where not enough disk space and some of the jobs were corrupted. I had been solved the disk space problem and I imported the backup jobs for those corrupted jobs. All the jobs are running properly after that except this scheduler.
I got this msg since that time when I encounter those problems.
Is this the reason why the DS scheduler getting problem???
Is there any idea please??? :roll:

Thank you so much,
ICE

ray.wurlod wrote:What happens when you open a cmd shell and type the AT command? ...

Posted: Thu Nov 01, 2007 12:40 am
by ICE
Dear All,


All of my schedule were gone itself and I have reschedule all the jobs. So I have solved this :)


Thank you,
ICE