Performace issue in job sequence run

Posted: Mon Sep 10, 2007 12:53 am
by koolnitz
Hi

We have a job sequencer containing 10 jobs in row. If a job finishes successfully, its successor job kicks off and there are no other triggers defined between the jobs.

Earlier, the sum of Elapsed time of individual jobs was quite near to the total elapsed time of the job sequence. Now, DS takes 2-5 mins (God knows for what!) after finishing one job and kicking off the next job in sequence. We have a major performance issue because of this.

Has anyone faced similar issue? Any help would be highly appreciated.

PS: We have checked with our Unix Admin and everything seems to alright at OS level. We have even had the server rebooted, but in vain.

Thanks!

Posted: Mon Sep 10, 2007 1:27 am
by Raghavendra
Please check if your &PH& directory is filled up. I remember once we had problems like this and we cleared the &PH& directory. Just check this out or wait for the expert comments.

Posted: Mon Sep 10, 2007 3:02 am
by ArndW
Along the same lines, check to see how big the log files of the 2 jobs in question are; purge them if necessary or ensure that the autopurge settings are enabled.

Posted: Tue Sep 11, 2007 11:35 pm
by Raghavendra
Nitin Jain,

Is the problem solved? If so can you please post the deatils how you solved the problem so that it will be helpful us in identifying the performance issues.