Post by chulett »

rivajtp wrote:but instead of terminator stage what i will suggest is let the otherwise link from all job activity go to sequencer and for 'Any' option. after that you put a routine activity stage and then use the routine UtilityAborttoLog routine in routine--->SDK---->Utility..

This is better i think rather make it too complex. What say chulett?
Chulett say - six of one, half dozen of another. Hmmm, sounds like fortune cookie. :wink:

Neither is more complex than the other to speak of. Both will work to abort the Sequence. Both can log a custom message when doing so. I'd prefer the Terminator stage (if your version supports it) for a couple of reasons. First, that is the purpose it was meant to fulfill and secondly it gives you the option to send stop requests to any currently running jobs. Plus visually it makes it more obvious what is going on in the design.

My two cents.
-craig