Job control process (pid 5976) has failed.

Post questions here relative to DataStage Server Edition for such areas as Server job design, DS Basic, Routines, Job Sequences, etc.

Moderators: chulett, rschirm, roy

Post Reply
sreddy666
Participant
Posts: 46
Joined: Tue Jun 29, 2010 8:28 am

Job control process (pid 5976) has failed.

Post by sreddy666 »

Hi Friends,

I am having issue with one of my server job DataStage 8.5.

Issue: Job control process (pid 5976) has failed.

Problem is i have logout some processes from director window- job- resource clean-up, for releasing some locks.

Now job status is showing as crashed.

Please advice me how to proceed forward.
a> can i delete crashed job and re-import the same job <or> do i need to rebuild from any config file.
b> this jobs is loading data to sqlserver database. so do i need to check weather that table or tablespace or datafile is locked?
c> there are some hash files in this job. so will they be locked.

Please provide your valuable inputs..

Thanks in advance.
chulett
Charter Member
Charter Member
Posts: 43085
Joined: Tue Nov 12, 2002 4:34 pm
Location: Denver, CO

Post by chulett »

a> Just Reset the job. If for some reason it won't reset, use the Clear status file option. Both are done from the Director.
b> Possibly. Check with your DBA. Note you may need to manually roll back any partial loads, depending on your job design.
c> No.
-craig

"You can never have too many knives" -- Logan Nine Fingers
ray.wurlod
Participant
Posts: 54607
Joined: Wed Oct 23, 2002 10:52 pm
Location: Sydney, Australia
Contact:

Post by ray.wurlod »

Another possibility is that someone or something killed the main process of the job.
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
sreddy666
Participant
Posts: 46
Joined: Tue Jun 29, 2010 8:28 am

Post by sreddy666 »

Thank You Ray and Craig,

i reset the job.. it is fine now.