Can't we set the limts on scheduled jobs?.

Post questions here relative to DataStage Server Edition for such areas as Server job design, DS Basic, Routines, Job Sequences, etc.

Moderators: chulett, rschirm, roy

Post Reply
naren6876
Participant
Posts: 233
Joined: Mon Feb 07, 2005 7:19 pm

Can't we set the limts on scheduled jobs?.

Post by naren6876 »

I have a scheduled sequence job which is aborted after 50 warnings eventhough I have set the limit as No Limit.

Can't we set the limts on scheduled jobs?.

Thanks in advance.
chulett
Charter Member
Charter Member
Posts: 43085
Joined: Tue Nov 12, 2002 4:34 pm
Location: Denver, CO

Post by chulett »

A better question would be - why is it generating any warnings? Unlimited warnings is not something I would allow. For whatever that is worth.

Where/how did you set the warning limit for this scheduled job? And by 'scheduled' I assume you mean cron via the Director interface, yes?
-craig