How to specify the number of nodes to execute Parallelmode

Posted: Thu May 26, 2005 9:58 pm
by Vijay Kumar
Hi,

Can we specify or set the number of nodes that a QS Job has to execute in Parallel mode.
In Data Stage we have the configuration file. In the same way can we specify the configuration file in Quality Stage in Parallel mode execution.

Regards
Vijay Kumar

Posted: Fri May 27, 2005 6:56 am
by ray.wurlod
Exactly correct. The APT_CONFIG_FILE environment variable specifies the location of the configuration file to use.