by Bryan.Tan
Sun Jun 25, 2006 8:54 pm
Forum: IBM<sup>®</sup> Infosphere DataStage Server Edition
Topic: Job Control fatal error (-14)
Replies: 25
Views: 16645

Thanks for the pointers Klaus. We have jobs running in parallel. Around 6-7 jobs at a time. That might be one of the problem, as you mentioned earlier. Just curios, is there a limit whereby Datastage could handle an "X" amount of parallel jobs running or is it based on the 60 seconds windo...
by Bryan.Tan
Thu Jun 22, 2006 5:00 am
Forum: IBM<sup>®</sup> Infosphere DataStage Server Edition
Topic: Job Control fatal error (-14)
Replies: 25
Views: 16645

I'm not sure why... cause we have a very powerful server Dual processor and 2 GB memory and there are no issues with the performance and resource of the machine.

In addition to that, some of the error message includes - "Abnormal termination of stage..."
by Bryan.Tan
Wed Jun 07, 2006 12:48 pm
Forum: IBM<sup>®</sup> Infosphere DataStage Server Edition
Topic: Job Control fatal error (-14)
Replies: 25
Views: 16645

Looks like I will need to Set the time for Inactivity in Inactivity Timeout box.

Thanks.
by Bryan.Tan
Wed Jun 07, 2006 12:36 pm
Forum: IBM<sup>®</sup> Infosphere DataStage Server Edition
Topic: Job Control fatal error (-14)
Replies: 25
Views: 16645

Job Control fatal error (-14)

I have a problem whereby the job was aborted. I checked the Log and it indicate the following error message:

Batch::<Batchname>.JobControl(fatal error from DSRunJob): Job control fatal error (-14)
(DSRunJob) Job <jobname> apprears not to have started after 60 seconds.

Kindly advice.
by Bryan.Tan
Sun Mar 05, 2006 7:55 pm
Forum: IBM<sup>®</sup> Infosphere DataStage Server Edition
Topic: CPI-C Initialization Failure
Replies: 5
Views: 3438

Hi Keith, Finally got it figure out what happened to the issue here. Root Cause: The SAP Dispatch/Gateway services configuration file found in the C:\winnt\system32\drivers\etc was not updated. The file contains information of the SAP ports that are supposed to be connecting Datastage server with th...
by Bryan.Tan
Wed Mar 01, 2006 9:34 pm
Forum: IBM<sup>®</sup> Infosphere DataStage Server Edition
Topic: CPI-C Initialization Failure
Replies: 5
Views: 3438

Here's the scenario: Currently, we've performing a migration from Server A (WinNT4) to a new Server B (Win2000). Server B was newly setup. All the application were newly installed (Datastage) A Project Export has been done from Server A to Server B. I've checked all the settings in Server B to be sa...
by Bryan.Tan
Wed Mar 01, 2006 12:52 pm
Forum: IBM<sup>®</sup> Infosphere DataStage Server Edition
Topic: CPI-C Initialization Failure
Replies: 5
Views: 3438

Hi Keith, We actually have another Datastage project running on another server (which was working perfectly fine). Yes. It was a new extract that we've imported from the previous server. The error struck us when we're setting up the same enviroment in the new server. All the SAP Logon and CPI-C sett...
by Bryan.Tan
Wed Mar 01, 2006 12:18 pm
Forum: IBM<sup>®</sup> Infosphere DataStage Server Edition
Topic: CPI-C Initialization Failure
Replies: 5
Views: 3438

CPI-C Initialization Failure

Hi Guys, I had an error when trying to perform an SAP Extraction using the ABAP Extract. "CPI-C Initialization Failure" I did a "Validate Stage" in the DS Designer, the (SAP Logon, CPI-C User and RFC Version check) was ok. Any idea if the installation of SAP Extract PACK v5.1 wou...